Routine operation procedure of air - flow ultrafine pulverizer

2022-01-21 15:06:19
times

About the operation procedures of the airflow crusher, the following by xiaobian will spend some time and energy to elaborate on this knowledge point, so that we know how to correctly operate this kind of machine and equipment.


The operating procedures of airflow mill, which includes:


1. No sundries or foreign bodies are allowed in the airflow crusher, because it will damage the equipment.


2. Before starting the equipment, check the lubrication of the bearing and reducer to see whether the lubrication is good and whether there are problems that need to be dealt with.


3. Check the amount of oil in the reducer box to see whether the amount of oil is sufficient, and how the oil feeding situation of each bearing refueling device is and whether it is normal.


4. Whether fasteners such as screws are fastened, whether blades are seriously worn, and whether they need to be replaced.


5. Whether the electrical switch and limit switch are in good condition and can work normally, and whether the protective cover at the coupling, belt and gear is in good condition and reliable, and whether the electrical facilities are sensitive and reliable.


6. When the airflow crusher is working, the operator can not leave without authorization, but can not contact the rotating part of the device, or move the protective cover at will, which is very dangerous.


7. When the grinder is in use, pay attention to whether there is any abnormal phenomenon at any time. In case of failure, the power supply of the equipment should be cut off immediately, and then handled by professional maintenance personnel.


The above is the airflow crusher operation procedures, as long as we master the above seven points, the airflow crusher will be able to normal service for us, and the life is more and more long.


The main contents of the safe operation rules of the airflow grinder are:


(1) All lines and electrical components of the airflow crusher should be checked to see if they can work normally.


(2) Whether the machine is grounded, so as to avoid the danger of electric shock caused by electrified shell.


(3) Whether the main shaft of the machine is stuck, if so, it should be handled in time.


(4) During the operation of the machine, whether there is any abnormal situation, if so, stop the machine immediately for inspection.


(5) Check the blade to see whether it is tightened and whether the blade clearance can reach the specified standard.


(6) Before using the crusher, check whether there are enough sundries or miscellaneous materials in the working room, and remove them in time if there are.


(7) Feeding can be started only after the grinder runs normally.


(8) The mill should stop feeding before stopping. The machine can not be stopped until it is completely finished discharging.


(9) Feeding should be uniform and not excessive, so as not to increase the burden of the machine.


(10) In the process of operation, the airflow crusher can not be cleaned, maintenance and other work.


Tags

Recently Viewed:

Contact us

Shanghai Huasan Powder Equipment Co., LTD

Contact person: Manager Zhu

Tel: 021-57460338/57460358/57468812

Mobile phone: 13818804871/18017628352

Fax: 021-57463615

Email:sales@huasanpowder.com

Address: No.33 puzhuang Road, Zhuanghang European Industrial Park, Fengxian District, Shanghai